Housing
The goal of the Housing Plan as part of the transformation of the Sharswood neighborhood is to transform the local distressed housing and vacant land into energy efficient, mixed-income, and affordable housing.
Sharswood Choice Housing Phases Map
Hunt-Pennrose Rental 1 Phase – 2000 block of Master St and 1300 block of N 21st St
60 units of housing (51 unit multifamily building and 9 townhomes)
30 units of PHA replacement housing and 30 units of affordable rental housing
24 one-bedrooms, 21 two-bedrooms, 15 three-bedrooms
Construction complete
Hunt-Pennrose Rental 2 Phase – Between Master and Jefferson Streets, 24th to 25th Street
59 scattered-site, townhouse units
30 PHA replacement units and 29 affordable rental units
Includes a community room and parking
1 one-bedroom, 28 two-bedrooms, 30 three-bedrooms
Construction Start: March of 2022
Construction completion projection: July of 2023
PHA Rental 1 Phase – 2300 and 2400 blocks of Master St and 2400 block of Ingersoll Street
58 scattered-site, townhouse units
All PHA Replacement Units
Includes a community center at 24th and Master Streets and parking
16 one-bedrooms, 10 two-bedrooms, 24 three-bedrooms, 7 four-bedrooms, and 1 five bedroom
Construction Start: July 2022
Construction completion projection: September of 2023
PHA Rental 2 Phase – Between 23rd and 24th Streets, Harlan and Stewart Streets
65 scattered-site, townhouse units
All PHA replacement units
Includes parking
12 one-bedroom, 22 two-bedrooms, 19 three-bedrooms, 11 four-bedrooms, 1 five bedroom
Construction Start: March of 2023
Construction completion projection: July of 2024
Hunt-Pennrose Rental 3 Phase – Between 24th and 25th Streets, Jefferson to Oxford Streets; between 22nd and 23rd Streets, Ingersoll and Master Streets; within Ridge Ave, Sharswood Street, 21st Street and N College Ave
224 Total Units - scattered-site, townhouse, and multi-family units
101 PHA replacement units and 88 affordable & 35 unrestricted rental units
Includes parking, a community room, and ground floor retail (6,800 sf)
47 one-bedroom, 94 two-bedrooms, 67 three-bedrooms, 16 four-bedrooms
Construction Start: March of 2023
Construction completion projection: July of 2024
Hunt-Pennrose Homeownership – Scattered Sites
100 scattered-site, infill homes
Construction Start: March of 2023
Construction completion projection: December of 2024
PHA Homeownership 1 – Scattered Sites
38 scattered-site, infill homes
Workforce Homeownership – 80-120% AMI with price cap
Construction Start: March of 2023
Construction completion projection: March of 2024
PHA Homeownership 2 – 23rd and Bucknell Streets, Jefferson and Oxford Streets
36 homes
Workforce Homeownership – 80-120% AMI with price cap
Parking
Construction Start: March of 2023
Construction completion projection: March of 2024
PHA Homeownership 3 – Scattered Sites
51 homes
Workforce Homeownership – 80-120% AMI with price cap
Construction Start: July of 2023
Construction completion projection: December of 2024